Meereskunde's Move into HdE

HdE außen HdE innen


Facts


Time of the Move

29 June - 10 July


Procedure

This is the general procedure of the move. The exact dates (i.e., Day 1 for each floor) will be published after 22 June.

When

Where

Who

What

Day 1 (e.g., Monday)

Bu53

All

last preparations and packing

Day 2 (e.g., Tuesday)

Bu53, HdE

moving company

move of packed and labelled boxes and furniture

Bau- + Raumbeauftragte - noone else!

contact persons

Day 3 (e.g., Wednesday)

Bu53, HdE

moving company

move of packed and labelled boxes and furniture

Bau- + Raumbeauftragte - noone else!

contact persons

Day 4 (e.g., Thursday)

Bu53, HdE

moving company

move of packed and labelled boxes and furniture

Bau- + Raumbeauftragte - noone else!

contact persons

Day 5 (e.g., Friday)

HdE

All

unpacking


Floor Plans

(click on plan to get a larger copy)


Q & A

Which company will do the move?

How have the offices to be prepared?

Will plants also be moved by the company?

When will the meeting rooms on floors 4 and 5 in HdE be available, and bookable?

When will I get my transponder?

When will we get the moving boxes and labels?

Will there by kitchens on both floors?

Will the posters in the corridors also be moved?